P6 not allowing selection of FS relationship between two tasks
I have read that the newest version so of P6 no longer allow invalid relationships between Milestones and predecessors/successors. We saw this on a contractor's schedule as they were sharing their screen. But P6 also would not allow him to select FS relationship between two tasks, not milestones. Anyone know why this might be?