Activities Do Not Move on Gantt
Can anyone help me figure out what I'm doing wrong? I can build a schedule in Primavera P6 v.18 just fine. However when I move an activity(because it hasn't started yet) The activities that follow it do not move in the timeline. Example: I built a schedule with a specific start date. That date has come and gone and the project has not started. I figured I could move the start date and everything else would automatically adjust. This doesn't happen. Thanks!