How Are Resource Remaining Units And Costs Calculated When Using Resource Curves?
I am using Primavera P6 Professional 20 version 20.12.0.37740
I have an activity resource spreadsheet that I use to determine remaining units and costs (cashflow) for our projects. I have a resource curve assigned to these activities but when the activity is a longer duration it takes the remaining material costs and splits the cost over weeks instead of on the % given in the resource curve.
- Actual Duration
- Remaining Duration
- Budgeted Cost
- Curve definition
The current one management is looking at is 832 days long in duration and I have a curve set to 20% at 0, 20% at 15, 20% at 30, 30% at 85, 10% at 100 but the remaining material costs for the 20% at 30% duration is split over 7 weeks. I would like this to be under 1 week or 1 month if possible.