Agreement rejected with errors that the customer is not assigned to the top task-FUNDING=PAIGT
Error: Agreement AGM_xxxxxxxx has been rejected with error The customer is not assigned to the top task. (FUNDING=PAIGT).The status of the agreement has been updated to Work In Progress.
Steps:
1. Ran intragovernmental Order Process
2. Ran Project G-Invoicing ECC Data Load
3. Created a Project- added / updated performance obligation line/schedules data (Capitalized Asset Indicator, Top Task Mapping, Servicing Agency TAS) (via ECC Dashboard)
4. Updated Agreement (via ECC Dashboard)
5. Update Agreement additional attributes (UDAs) - Enter Servicing Agency Funding Approval, Program Approval, Preparer Name, Email, Phone, Title information.
6. Submit Agreement Workflow Approval (AME)
7. First approver received WF Notification and Approved it