E1- ETO- Once the PO is created, is it possible to modify the requisition to add a new line?
The requisition was created by the project Manager(ETO).
The buyer generated the PO from the requisition and printed it.
The supplier asked to add a fee for the transportation.
The buyer added the fee on the PO but it is not printed on the PO.