Work Orders Dates changed on Completed Operations?
Work order have 10 operations. First 4 operations are completed on Aug-13-2022
Remaining 6 operations have 'First Unit Start Date' and 'First Unit Completion Date' in future dates.
Opened the 'Job/Schedule Details'-> 'Operations'-> Query WO -> Use the RESCHEDULE button to change the dates on 'Remaining Quantity Operations'.
Put the new date Sep-25-2022 and save the record.
Issue:- It updated the dates on remaining quantity operations but also changed the dates on 'Completed Operations'.