Can ASCP suggest to change the items in a work order
For example, the situation is like this. We have a work order to use a raw material A, there is no existing supply for item A. In the BOM, A has a substitute item B which has excess on hand.
In such situation, ASCP will suggest a planned order to buy item A and leave the item B excess. What we want is ASCP suggest us to change the work order and use the item B(consume the excess quantity of item B)
Do you have the same topic in there? May I have your suggestion about how ASCP support this scenario or any workarounds are welcome as well.