Preventive Mainteanace scheduling
We have defined a PM definition as below
And the results expected is
First Activity (TESTPM02) 7 days work order should be 13th of oct as the last service date is 6 th of oct . Work order got forecasted as expected
And the Activity (TESTPM03) first 14 days work order should be on 15 th of oct . But forecasting is suggesting work order at 20th of oct is it the indent behaviour
I understand that it is taking the last service information for both activities as 6 th of October and suggesting the work order is it correct?
Are we able to update last service check box for both the activities