Hi,

We did QA upgrade from IP2016 to 21.12. As the testing progresses we have some fixes made in Dev. My question is do I need to run an incremental migration from Dev to QA or a full migration from Dev to QA?

My understanding is since the QA has the data from Dev during its upgrade I suppose we only need an incremental migration. Please clarify.


Thanks,

Gb