PO Promised DATe VS actual REceipt DATE
Hello Group.
I have another Question.
We want to Evaluate our suppliers based on the PROMISED DATE entered on the PO. Is there a report or an SQL script that could give me both the PROMISED DATE (5-march-2023) on the PO, Versus the ACTUAL RECEIVED DATE (i.e. 2-March-2023). I want a report that will tell me if the supplier delivered on time or not based on his PROMISED Date!!
Thanks again
Regards
Philip