P6 Professional r22.12 Check Schedule Report: BEI Baseline Activities Count Incorrect
Hello,
I am trying to run a Check Schedule Report in P6 Professional r22.12.
The Tools | Check Schedule Report feature does not count the correct number of schedule Project Baseline Finish Dates before the 29-Feb-2024 data date.
In the below Check Schedule Report the Baseline Activities count (6) is the same as the number of Project Activities (6), as per the status date.
However, the correct number of Baseline Activities is eleven, as per the below screen shot of the P6 schedule.
The BEI should compute to 6/11 or 0.55. The schedule fails the DCMA 14-Point BEI ratio assessment.
Is this a bug in the Check Schedule Report feature?