How to implement Preventive Maintenance based on meter reading
Hi All,
We have a requirement work order should be generated using Preventive Maintenance based on meter reading entered on asset. Please see below details.
- Preventive Maintenance set up based on meter for 100 hrs., 1 hr per day.
- Business is entering daily hrs. running of genset on asset>enter meter reading
- If any day genset run 5 hours they are adding 5 hrs and then forecasting should be 100-5 days.
- But if we enter asset meter reading 5 hrs. then forecasting is showing on 106 days instead of 95 days.
Please suggest
0