OPC option to show Gantt as a "Timeline" with Activity Code colors?
Hello,
Working on a High Level Master Schedule for management. They want to see project phases broken out by color as 1 timeline. I have Programming/Design/Permit under 1 Activity Code, Construction/Cx another Activity Code, and Move-in as another Activity Code. Each Activity Code separate color.
The Gantt Chart looks fine, but managements wants to see 1 line with the Colors shown.
What are my options in OPC? Does this "Task" upgrade provide this capability?