Double Forecast Consumption
Oracle Products : Oracle E-Business Suite
Versions : R12.2.5
Question :
I have a problem in forecast consumption.
The problem is, there is a duplicate consumption by the same sales order with the same line.
the forecast bucket type = weekly , Backward Days = 365 , Forward Days = 10
Step1 : create a forecast , forecast date = 2023/06/05 , 3000 PCS
Step2 : create a order_A , schedule ship date = 2023/06/05 , 1400 PCS
Planning Manager consumed forecast 1400 PCS , the forecast remain 1600 PCS.
Step3 : change order_A , schedule ship date = 2023/06/22 , 1400 PCS.
Planning Manager consumed forecast 1400 PCS , the forecast remain 200 PCS.