Auto-Schedule Primavera Schedules on Import
Hello, The Microsoft Project integration settings has the ability to schedule projects after synchronisation. This is a great option to have.
However there doesn't appear to be any option to do this for Primavera XML and XER imports. Is this the case?
At times this is frustrating because until you reschedule the imported Primavera schedule, the float and longest path does not calculate properly among other things.
So it would be good to have this option available for Primavera imports too.
Additional note - this would be another improvement over P6 as P6 doesn't do this either :)
OPC Version 23.6
Microsoft Project Integration Import Parameters