Resource Rate 2 column

I'm looking for ideas on how to meet this requirement.


  1. Resources have rate 1 as the internal rate
  2. Resources have rate 2 as the "sell rate"

I would like to see the planned total cost for resources in the activity view for both rate 1 and rate 2. OPC only shows one rate as configured on the project settings.

My current work around is to apply rate 2 rates on resources in a "rate 2 scenario" then use schedule comparison to compare between rate 1 which is in the current schedule vs rate 2 in the "rate 2 scenario". I then download the comparison in excel for further analysis.