Service Request: Planned Task Duration Calculation
Oracle EBS
RDBMS : 12.1.0.2.0
Oracle Applications : 12.2.9
Currently the task planned effort is based upon the task type effort (UOM and Duration). We would like a method that this is calculated based upon the task type and the equipment type for the task.
For example:
The same task type of dispatch and service request type of maintenance is used for the below customer visit.
A maintenance visit for a furnace, the effort is 2 hours. Item = FURNACE
A maintenance visit for an ATM machine, the effort is 4 hours. Item = ATM
Since there are many models of the item, it would make sense to use an item category to be able to assign effort to the task