Original BaseLine dates - fields for report
Oracle Primavera Cloud
Hello, I'm designing a report that will help us compare current and forecasted dates vs Original Baseline dates.
When selecting the fields, the system allows to choose only the following fields: Start (Baseline), Finish (Baseline), Planned Start (Baseline), Planned Finish (Baseline) but none of those are showing the dates of the Original baseline.
Report design:
Report Layout:
Result:
Actual project (Same activities, different order):
Thank you in advance,
Víctor.