Hello, I'm designing a report that will help us compare current and forecasted dates vs Original Baseline dates.

When selecting the fields, the system allows to choose only the following fields: Start (Baseline), Finish (Baseline), Planned Start (Baseline), Planned Finish (Baseline) but none of those are showing the dates of the Original baseline.

Report design:

Report Layout:

Result:

Actual project (Same activities, different order):

Thank you in advance,