Hi, I have Resource A (RA) and Resource B (RB).
RA is assigned on an Activity and I want to substituite RA with RB: when I do it, all the RB's planned unit are fully saturated and I don't have any evidences of the previous planned to RA.
We need to change the resource assigned but keeping the previous planned unit. How can we do it?