Why does the simulated M cost roll pull the simulated P cost instead of the frozen P cost?

edited Sep 22, 2023 9:50PM in Manufacturing - JDE1 (MOSC) 4 commentsAnswered

Hi

In JDE E1, 9.2 - I've noticed that when running a simulated manufactured cost process, R30812, the simulated cost of the component (P item) is pulled, instead of the frozen cost component.

In usual circumstances, the simulated and frozen component costs would be the same, but if a user entered a new simulated component cost (P item) and didn't freeze it, then this would cause a problem, as I would expect the process should be that the frozen cost is pulled into the M item.

Is it correct that simulating a new M cost should result in the simulated P cost being pulled, or is this a bug, or processing option that should be changed to use the frozen P cost?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center