Hi everyone

I am testing the materials planning module and have a couple of questions with regards the proper set up of some processing options of the R3483.

I ran a generation type "1" over MPS items to create work orders and now I want to run the R3483 again with generation type "5"

1- After generation type "1", where I have created WO for MPS items, Do I need to freeze these new work orders before the generation type "5"?

2- For a generation type "5", What is the proper set up of processing options "1" and "2" under the Performance tab? Do I need to clear or not?