E1:34 R3483 Is generating ordering messages with past dates
JD E1 8.11
Hi everyone
I am testign the R3483 and I have a question, after generating the report and viewing suggested messages in the P3411 application, I noticed that some "O" and "B" messages have the start date and/or the Requested date, one day before the current date (generation date), so when I am trying to process those suggestions to create work orders or purchase orders the error Requested date is less than start dates is showing up (I know that this valid error message), so my questions are:
Why is the R3483 suggesting messages with past due dates (start and requested)?