Hi all,

I have a question related to the costs that we see in cost history.

So, I've created a job with 5 Serial Numbers. Only for one SN I've issued the components and then performed move and complete.

In the following picture, in blue we have the 1st SN (material issued and then performed move and complete).

The other 4 SN's just issued one serialized component for each of the Assembly SN's and then performed Move and Complete.

The job is not closed, but my question is why we have zero material cost in the last SN (this happens with all jobs completed and there is still material not issued).