How to trigger notification to Unifier group for Activity sheet refresh from P6?
Is there a way to trigger a notification to a Unifier group for Activity sheet Refresh from P6?
we've a requirement where Gateway integration to refresh Unifier Activity sheet data from is scheduled monthly, but once refresh completed, we want to notify Project Manager, Planners (which are a group) in Unifier.
In Gateway we've an option to send a email based on synchronization status, but that will go to the static email id. and not linked to Unifier groups.
Is there any other way to achieve this in Unifier?