Planned Start and Planned Finish
Is there a way to lock in the planned start and finish dates in OPC? The way our company schedules projects is we do not progress the schedule using the data date. The issue I'm having is whenever I mark an activity as started in OPC and schedule the project, the planned finish dates move up to before the planned start. I'm assuming this is because the planned finish is going off of the Data Date. Is there a way I can lock in the Planned Start and Planned Finish Dates?