Scheduling Using Actual Dates

Scheduling a project this way is very unorthodox and extremely incorrect however this is how my company wants it done.

My question is, I'm using actual dates to schedule our projects instead of retained logic because my company does not want to move planned dates. However, when I press schedule the Late Start and Late Finish on some activities start and finish sooner than the Early Start and Early Finish dates. This is causing the Total float to be incorrect. Is there any idea what can be causing this or what could be moving these dates? Please see the image below. its only occurring on these 2 activities.