R3483 - For 52 weeks, Job goes into Error.
JD Edwards E1 9.2
We are running R3483 (MRP / MPS) report every day.
Processing options are -
Past Due= 2 , Planning Horizon = 52 weeks
Gross Generation
Clear F3411/F3412/F3413 = 1
Multi facility - Date Branch = Blank
Is it because of 52 weeks or Date Branch ?
We have 10 BPs, some are having 5 day calendar & some are 7 day calendar.
How we can setup?
Regards,
Rajendra Prabhune
JDE Consultant