R07520 Purge Leave Requests
Hi Community,
When we run the R07520 Purge Leave Requests UBE to purge old leave requests, the UBE is not working as how we'd expect. For example, in the Processing Options, we've put purge any request PRIOR to 1/1/2010, but when we review the output, it has Leave Begin/End dates on there from AFTER 1/1/2010, such as dates in 2016, 2018, 2023, etc.
Does anybody know what dates are driving that Processing Option? See examples below. Is this expected? I would think that no dates after 1/1/10 would be on the report.
Notes: We have tried adding new versions, thinking maybe the version was corrupt, but have the same outcome. We tried submitting specs only. Same outcome. We've changed the PRIOR TO date in the POs and the report changes the output, but we still get dates that are AFTER the Processing Option date. See example below.