Client is having a business scenario as below
Contract Amount= 12,000,000 AED
Advance= 30% of contract value
Retention = 10% of contract value
1st Invoice: Advance Invoice of 3,600,000 AED as per contract agreement
2nd Invoice: Progress Billing
Advance Recovery= 720,000 AED
Retention Recovery= 240,000 AED
Revenue =2,400,000 AED
Receivable= 1,440,000 AED
Retention Release
1,200,000 AED at last billing
how to achieve this in project billing in fusion