Primavera P6 Labor Resource Mapping
Hello, I am operating on version 18 of Primavera P6. I am wanting to know if this version has the capability to split a labor resource to two different activity codes- the same labor resource is being funded equally by two separate parties. Instead of creating two separate activities, adding the same labor resource needed and coding them accordingly, is it possible to load a single activity with the labor resource and coding half to one activity code and half to another? Additionally, if not available for version 18, is this available for any later versions of P6?
Thanks