Update Activity Status within Scenario
I have a project where the prime contractor issues a monthly update via XER (we are a subcontractor.) I have been importing the XER monthly which updates the "Current Schedule" in OPC. (I snap baselines every time of update for reference).
I developed a scenario based on the February update (Data Date 3/1/24). We have received another schedule update (Data Date 5/1/24) that I have uploaded into the current schedule. Is there a way to progress the activities in the scenario using the status from the 5/1/24 update? When I open the schedule, status is frozen based on the 3/1/24 update.
Alternatively, is there a way to copy one WBS node from the scenario into a new scenario that I create based on the 5/1/24 update?