Duration % Complete not calculating on Level of Effort Task

edited May 30, 2024 10:41PM in Primavera (MOSC) 4 commentsAnswered

Can we expect Duration % Complete to calculate on a Level of Effort Task? I am seeing 0% when a LOE task has actual start in the past and remaining duration in the future. There's one task that reads 0% and another that reads 22.58%. Both are in the same project. It's unclear what's causing this.