Transitioning from a Project to a Program with many Projects
Hello
I'm quite familiar with P6, but have only been using Primavera Cloud for a few months. I inherited a project that is really 40 projects. I need to break it into a program (which I have set up) with 40 projects in it.
There must be an easier way of doing this then what I'm finding.
The two options I see are to a) open the old large project and new project in a program, and copy and paste, but loose the WBS, or b) add each WBS from project, which would be tedious based on the way this schedule is set up. (program procurement is up top, so each piece of equipment is broken into 40 projects, times each equipment piece).