Can I run the R3483 simultaneously without the parallel option or specific key definition?
Case: the clear option is scheduled during the night, followed by sequential versions of different companies.
During the day, manual processing can be started to recalculate the MRP messages. There are two different company structures, completely separated from each other also defined in the data selection of the R3483 versions:
- Company A - branches 1 to 8
- Company B - branches 10 to 18
Is it possible to run the R3483 recalculate batch simultaneously for both companies? Or should the "Set Key Definition" options on tab 7-Performance be configured in order to have a correct (re)calculation?