How do I set an Imported P6 Baseline as the Original Baseline in OPC
I am migrating projects and baseline schedules to OPC from P6 EPPM. How do I set an imported baseline schedule as the original baseline in OPC? The baseline is present under Schedule\Baselines, but I cannot do anything beyond deleting it or exporting it to P6.
Christine
Oracle Primavera Cloud
24.6.5.0 20.06.2024.0553