Can I recalculate costs for a group of projects?

We are migrating from P6 EPPM to OPC. We are using the Migrate Projects integration. I need to recalculate costs for over 1250 migrated projects. I thought I would be able to do this in conjunction with placing the projects in a program and scheduling the program, but after successfully scheduling a program containing 108 projects, I realize that despite checking the box to Recalculate costs upon completion, the scheduling log for the program reads "Recalculate costs upon completion: No. Recalculate costs can't be run from within a program."

Is there a way to recalculate costs other than individually opening each project?