ref doc- E1: 34: Planning Fence Rule and Days, Freeze Fence and Message Display Fence (Doc ID 655578.1)
Leadtime for the Parent SKU is 20 days. With Planning time fence rule of C how many days in the planning fence days are recommended that I set up?
To note that this below is our timeseries horizon
and also if the lead time is 10 days with the planning fence rule of C how many days in the planning fence days are recommended that I set up?
PS- I ask this to know what is the precise relationship of planning timefence days with its lead time? Because