Resource - Calculate Costs from Units Checkbox Option
Hello Team,
I have 2 burning question which I didn't get answer by searching the OPC help.
When assigning resource to an activity,
1. Is there a way to uncheck the tick from "Calculate Costs from Units" Box ? It comes as ticked by default.
2. Can we make Planned cost default setting to 0?. Currently the planned is defaulted as Duration x planned units.
TIA.