Calendar based schudel maintenance doubt
We are creating calendar based maintenance schedule for an asset
there are 4 activities for this asset
Monthly, 3 Monthly, 6 Monthly, Yearly and the work order should be created on 1st of every month
I have created schedule definition with proper suppression and when we expect yearly after 12 months after today, it is working fine i.e as below
M, M, 3M,M,M,6M,M,M,3M,M,M,Y
Whereas the other case i have created the schedule definition but we want yearly in the month of July next year, so it should come in the below sequence if we are forecasting today