"Critical Path Number" - P6 EPPM 23.12 (Client)
Using P6 client (for EPPM) 23.12.1.48893
How are the "Critical Path Number" column/values calculated and populated? I am trying the new 'Activity Critical Path' toolbar and cannot seem to get the "Critical Path Number" column to populate.
I cant find any reference in the Oracle docs except here which doesn't go into detail for this column:
Schedule settings are:
- Ignore relationships…unchecked
- Open-ended…unchecked
- Retained logic
- Define critical as… 0h
- Calculate float based on…. Each Project
The schedule I am testing with has a clear critical path, and additional activities with float. Everything is linked.