P6 EPPM - Resource and Role Cost Spreads Consider Rate Changes Over Time - Negative remaining units
Hello
Considering this recent feature (for us), we experience an issue when the setting "Cost Spread" is set to "Units Spread"
For positive remaining units, it works very fine and as expected :-)
But, when we have negative remaining units, the total remaining cost is correct but in the resource assignment spread view for example, it does not display the remaining cost per period (e.g. per month)
Have you experienced this issue?
Hopefully have you solved it? :-)
We are using P6 EPPM R22.12.10
Thanks in advance