Check Schedule Report Defaults (P6 Eppm)
I'm looking for some help to see if it is possible to change the defaults for the Check Schedule Report. I know I can change the defaults for a specific schedule by changing them and then saving them. However, when I open a different schedule, it goes back to the defaults and I have change them again and save them to that specific schedule. I would like to change the defaults that come up for any project before saving anything
Attached is a screen shot of the current defaults. Is there a table in the background of P6 where we can change these permanently.