Leveling resources in Scenarios
We have a resource loaded schedule where we want to play around with different "crashing scenarios".
Unfortunetly it seems that when working in scenarios it only handles dates and durations; not resources.
Are we doing anything wrong or looking at the wrong place? It seems that being able to see the resource load in scenarios would be a pretty standard expectation as we can then look at cash-flows as well.