one of our payroll user ran into an issue while running the payroll final update (R07250)
Job completed successfully but failed to trigger any of the subsequent jobs R053951,R053953,R07411Z1 and R04110ZA except for R07354 (this is only job that shows as completed). we couldnt find any errors in the logs and there is no trace of what happen to these jobs. Has anyone encountered this situation? If so, what was identified or possible resolution? This is a first instance this occurred since we upgraded to 9.2.8.1 so was wondering if there is a known bug in the TR. etc. couldnt find any documentation related to this. Please share your valuable feedback.