PR - 2 lines of Same Item# when released by ASCP

The Purchase Requisitions created from the ASCP, has 2 lines of Same item# but different with need by dates. But the profile MRP:Requisition Load Group Option is to One each.

So In this case, the PR should have one line each, but in our case we are having 2 lines of the same item# in an single PR with 2 different need by dates.

Example:

PR# 1234

PR line# 1 - Item A = 50 Qty - Need By date : 20-Nov-23

PR line# 2 - Item A = 50 Qty - Need By date : 21-Nov-23

Any advise. Thank you in Advance.