Hi,

I have the following BOM setup:

FG-1

- RM-A -->RM-A1

- RM-B

FG is the finished goods and RM-A and RM-B are the components and RM-A1 is the substitute of the RM-A.

When I ran the ASCP, I checked the “use substitute components”. And I also set the max order quantity to zero for RM-A1 based on the suggestion from note 1446564.1.

FG-1 has no onhand

RM-A has no onhand

RM-A1 has onhand 50 Pcs

I have a MDS with FG-1:

Week 1: 200 Pcs

Week 2: 100 Pcs

After running the plan, the system suggest:

Week 1: RM-A1 150 Pcs

Week 2: RM-A 100 Pcs

I checked the pegging information and found that it seems all demand for week 1 is using RM-A1 if the substitute component is used. I want the system to use 50Pcs onhand on substitute RM-A1 but generate 150 Pcs planned order for primary component RM-A. Is it possible?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center