How to configure Primavera Cloud to automatically calculate Remaining Duration based on the Data Dat
Tool Oracle Primavera Cloud
Vesrion 24.1
Hello everyone,
I’m encountering an issue in Primavera Cloud, and I’d like to know if there’s a specific setting or configuration to make the software automatically calculate the Remaining Duration of an activity based on the Data Date.
Here are the details:
- I have set the Percent Complete Type to Duration.
- When I update the Data Date, OPC does not seem to automatically recalculate the remaining duration based on the elapsed time. The remaining duration remains equal to the initially planned duration unless I update it manually.
What I’d like:
- Primavera Cloud to automatically adjust the remaining duration based on progress and the Data Date without requiring manual updates each time.