Will F4074 UPRC being updated if adjustment details is set as '3' % of cost, and after cost updated
We are using weighted average cost.
We setup price adjustment with '3' % of cost.
Created a sales order and F4074 is generated with BSCD = '3' and UPRC.
There is cost change as new PO is received with new cost.
During shipment confirmation, the unit cost on sales order is updated with new weighted average cost.
However, we found the UPRC on F4074 is not updated.
If there any way to update F4074 based on update unit cost of the sales order?