[OPC][Risk] Clarification on Durations and Calendars in the Risk Register

edited Feb 5, 2025 3:12PM in Oracle Primavera Cloud (MOSC) 1 commentAnswered

Product : Oracle Primavera Cloud / Risk Module

Hello everyone,

I have a question regarding how durations and calendars work in the Risk Register module of Oracle Primavera Cloud.

  1. Are the durations entered in the Risk Register expressed in working days or calendar days?
  2. If the durations are considered working days but the risk is assigned to an activity with a 7-day/week calendar, which calendar will be used?
  • The specific calendar of the activity to which the risk is assigned?
  • Or the project’s default calendar?

Based on my research, here is my current understanding (could you confirm if this is correct?):

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center