OPC Risk Module:Does Monte Carlo analysis in Oracle Primavera Cloud work this way ?
Product : Oracle Primavera Cloud - Risk Module
Hello,
I have researched Monte Carlo analysis—can you please confirm if it works this way in Primavera Cloud?
When a risk is assigned to multiple activities in Oracle Primavera Cloud, Monte Carlo analysis considers the uncertainties and potential impacts of this risk on each affected activity.
»»» The impact of the risk is applied to each affected activity in every iteration, which may extend or shorten their duration.
When an activity is associated with multiple risks in Oracle Primavera Cloud, each risk is considered individually and in combination to assess its overall impact on the activity.